Construction Activities Schedule

For recorded update information, or to speak to a representative regarding construction activities, please call Iroquois' Landowner Hotline at 800-253-5152

MILFORD

Activity

Begin

Anticipated
Completion

Site Preparation
(Clear, Fill, Grade)

Mid May 2008

June 2008

Foundations

June 2008

July 2008

Construction of
Compression Facility

July 2008

November 2008

Commission Facility

December 2008

December 2008

In-Service

January 2009

January 2009


NEWTOWN

Activity

Begin

Anticipated
Completion

ROW Preparation
(Clear, Grade)

June 2008

July 2008

Pipeline Construction

July 2008

September 2008

Commission Facilities

October 2008

October 2008

In-Service

November 2008

November 2008


Scheduled activities are subject to change based on weather and other conditions.


Contact Us

 

 

 

 

 

Topics of Interest

08/09 Expansion Project



Copyright 2008. Iroquois Pipeline Operating Company. All images & photographs. All Rights Reserved.
Legal Notice | Privacy Policy. Please direct technical comments or questions to webmaster_ma@iroquois.com

Website By: Axxiem